With Three Months Delay and a "Loss-Making" Contract
Navantia has today delivered the tanker “Monte Udala” to the Ibaizábal Group, doing so with three months of delay from the initially planned schedule. This fact highlights that the production machinery of the Puerto Real shipyard is not sufficiently lubricated to meet contractual deadlines, as their immediate competitors do, or that there have been failures in the forecasts by their managers.
It is the first of the four tankers “at a loss” that the Cádiz shipyard has under construction, based on the contract signed in 2015. It has been sponsored by Mónica Aznar, and the ceremony was attended by the president of SEPI, Pilar Platero; the president of the Ibaizábal Group, Alejandro Aznar; the CEO of CEPSA Corporate, Pedro Miró; and the president of Navantia, Esteban García Vilasánchez. The ship will join CEPSA's service under a “time charter” contract.
According to Navantia, the construction of each ship involves just over 725,000 hours of work, which translates to an average of about two thousand people, both direct and indirect employment. The second and third tankers in the series are already in the dry dock of the Puerto Real shipyard, at different stages of construction, and are also affected by delays in the production processes.
Photo: Navantia